KLASS LOOCH ASSOCIATES on-line.

Occupational Health & Safety Legislation Consultants 

         Established 1986

 

Tel 0117267839 / 0825749882                                                                                                                                      Fax 0866500687 

                                                                                                               

   November 2008

 

About Me

 

 Mission Statement

 

Contact Me

 

 Home

 

Services

 

Bronze Subscribers

 

Silver Subscribers

 

Gold Subscribers 

 

 Platinum Subscribers

 

 Summary of Subscriptions

 

Subscription Order Form

 

OHS News

 

Department of Labour (DoL)

 

Department of Mineral & Energy (DME)

 

OHS Chat & Skinner Newsletters

 

OHS Practitioner Newsletter

 

 Exclusive Subscriber Newsletter

 

OHS Act Section 16

 

Employer's Rights

 

OHS Act Section 37

 

OHS Court Cases

 

OHS Act

 

Department of Labour

 

ISO

 

Acts-on-line

 

SABS Website

 

Compensation Commissioner

 

 ASOSH

 

   Department of Justice

 

 Department Mineral & Energy

 

 

OHS Act Construction Regulations 3. Notification of construction work

(1) A principal contractor who intends to carry out any construction work shall -

(a) before carrying out that work, notify the provincial director in writing of the construction work if it includes -

(i) the demolition of a structure exceeding a height of 3 meters; or

(ii) the use of explosives to perform construction work; or

(iii) the dismantling of fixed plant at a height greater than 3 meters.

(b) before carrying out that work, notify the provincial director in writing when the construction work -

(i) exceeds 30 days or will involve more than 300 person days of construction work; and

(ii) includes excavation work deeper than 1 meter; or

(iii) includes working at a height greater than 3 meters above ground or a landing.

xc(2) The notification to the provincial director contemplated in subregulation (1) must be done on the form similar to Annexure A to these Regulations.

(3) A principal contractor shall ensure that a copy of the completed form contemplated in subregulation (2) is kept on site for inspection by an inspector, client, client's agent or employee.